1.1 Historical Context

Figure_1-1

Figure 1.1: 3D Render of completed building

1.2 The Structure

Figure_1-2

Figure 1.2: Revit model building overview.

1.3 Modelling and Analysis

Concept design generally done by hand, excel, MEMDES and other rough tools.

Figure_1-3

Figure 1.3: ETABS model for office gravity structure and lateral load resisting system.

Preliminary/Detailed design ETABS Model for office structure

Figure_1-4

Figure 1.4: ETABS model for office first-floor.

Figure_1-5

Figure 1.5: SAP2000 model for foundation design - bending actions.

1.4 Construction

We completed the drawings while overseeing construction. That had a lot of complications as well. I took two months to stay in Whangarei during construction.

  1. Screw piles installed then capped
  2. Ground beam reinforcement laid, including starters to slabs and precast panels
  3. Ground beams poured. Slab reinforcement laid. Figure_1-6
Figure 1.6: Congestion in the ground beams.
  1. Review precast panel prefabrication drawings. Precast panels delivered and propped.
  2. Ground slab poured.
  3. Review steelwork prefabrication drawings. Portal frame legs installed, followed by spliced portal beams.
  4. Gravity columns and beams supporting internal office structure installed.
  5. Various additional elements installed; roof purlins, tension bracing, additional supports to mezzanine floor.
  6. Mezzanine floor ribs, formwork then pour. Slab poured above.
  7. The workshop side had other elements as well, which I haven’t covered, such as wind beams for garage doors, and the canopy structure.

By the end of it all we were as glad as we were relieved to sign the final paperwork certifying construction. And last I checked the building hasn’t settled yet!